Neepawa Health Centre: We completed all of the site work preparation as we stripped topsoil to allow for construction to begin on the building of the new hospital. We installed gravel for temporary parking lots and built a road to allow for access to the site. We installed sewer and water, along with water services, manholes, and land drainage piping. We assisted with trenching for electrical conduits and the main power feed to the generator building. We performed subcuts and installed the necessary granular structure to build the parking lots. We excavated the planting beds and installed topsoil and also installed sub base material for sidewalks and created berms.
Gillam Airport: Installed a duplex grinder pump septic tank. Connected to an existing water line. Installed a fire hydrant. Installed a new sewer line service to the airport and shop.
New Neepawa Hospital Roadway: We installed catch basins and associated piping to deal with rain water and a sub grade drain to capture ground water and help to keep the road structure dry and structurally sound. Excavated and installed soft sub-grade and filled with rock to make a firm base for the future asphalt. We performed sub-cuts, installed gravel, prepared the base, installed geotextile, stripped topsoil, placed topsoil, and installed a culvert.
Neepawa Lift Station: Installing manholes, a forcemain, sewer line, water line, fire hydrants, and a lift station
Gillam Fox Lake Cree Nation: Installed sewer, water, and land drainage piping. Installed 26 services for future houses.
Nisichawayasink Cree Nation: Clearing and grubbing of site. Built a new road. Installed sewer and water main services.
Virden Rutledge Street: Renewed water and sewer mainline services.
Holland: Ploughed/ directional drilled in a 11km stretch of raw water line. Connected to 2 wells, and connected to the water treatment plant.
McLaughlin Private Sub Division: Installed water and sewer mainline and services, installed a fire hydrant, installed 2 manholes, and connected to an existing manhole. Installed 12 sewer and water services for future housing.
Oberon Well: Installed a 5km raw waterline from pumps and connected to an existing waterline. Installed a meter chamber.